HorizunMsProjectMcp 1.0.2

dotnet tool install --global HorizunMsProjectMcp --version 1.0.2
                    
This package contains a .NET tool you can call from the shell/command line.
dotnet new tool-manifest
                    
if you are setting up this repo
dotnet tool install --local HorizunMsProjectMcp --version 1.0.2
                    
This package contains a .NET tool you can call from the shell/command line.
#tool dotnet:?package=HorizunMsProjectMcp&version=1.0.2
                    
nuke :add-package HorizunMsProjectMcp --version 1.0.2
                    

Horizun Project MCP

build and test

An MCP server for Microsoft Project that needs neither Java nor Microsoft Project — and tells you the truth about what it wrote.

Point any MCP client at a .mpp, a Primavera .xer, or an MSPDI .xml and ask real questions: where the critical path runs, which resources are overbooked, whether the schedule would survive a DCMA audit, what a two-week slip actually does to the finish date. Then write changes back — and know which ones landed, because every one is re-read from the model before it is reported.

dotnet tool install -g HorizunMsProjectMcp

That is the whole install. No JVM. No Microsoft Project. No licence. It reads and schedules on its own.

NuGet


Why this one

There are a handful of Microsoft Project MCP servers. Every one of them requires Java, or a licensed Microsoft Project install, or a paid JDBC driver — and on the machine this was built on, none of them would start. Seven things here are not available anywhere else:

Zero prerequisites A single .NET binary. MPXJ is compiled to .NET through IKVM, so there is no JVM anywhere in the picture, and no Microsoft Project either.
Verified writes Microsoft Project silently ignores writes all the time — auto-scheduled dates, hard constraints, summary rollups, calculated costs. Nothing here is reported as applied until it has been read back out of the model and matched.
DCMA 14-point assessment The industry standard for judging whether a schedule can be run on. The Primavera servers implement it; none of the Microsoft Project ones do. Check 12 genuinely injects a 600-day delay and measures what moves.
It recovers logic nobody linked A schedule laid out correctly on the bar chart but never linked is the most common defect there is: DCMA flags it, nothing fixes it. The dates already state the order — this reads it back out, verifies the same order holds across every repetition, and proposes the missing links.
Reprogramming that is measured Recovery options are applied to a copy of the schedule, rescheduled, and reported with the finish date they actually produce. An option that recovers nothing says so instead of being offered as advice.
It learns from your past projects Point it at finished schedules and it reports what each activity really took and what usually precedes it, then drafts a new programme from that — one task per unit, sequenced the way the trades actually followed each other.
A BIM bridge Tie schedule tasks to model elements by code, turn measured quantities into duration proposals, and emit the per-element dates that drive 4D in Navisworks and the progress dashboard in Power BI. Nobody else does this at all.

The 25 tools

Sessionproject_health · project_open · project_save

project_health is a doctor, not a ping. It detects Microsoft Project, tests whether its COM server actually starts, and when it does not, hands back the HRESULT diagnosis and the repair steps. That is not hypothetical: this machine hit CO_E_SERVER_EXEC_FAILURE with a perfectly valid registration, and step one of the repair path it emits is what fixed it.

Readingproject_info · tasks_query · links_query · resources_query · timephased_query

Filtered, paged, field-selectable. Tasks are addressed by their stable uid; the row id is display only, because it shifts the moment a task is inserted and addressing by it edits the wrong task.

Analysisschedule_analyze · schedule_qa · baseline_compare

Computed server-side, so the agent asks a question instead of pulling two thousand tasks into context. Critical path, float distribution, driving path, day-by-day overallocation, DCMA-14, and full earned value (BCWS/BCWP/ACWP, SPI, CPI, EAC, TCPI) — denominated in cost where the schedule carries costs, in work hours where it carries hours, and weighted by duration where it carries neither, which is most of them. The report says which.

Writingtasks_write · links_write · resources_write · calendars_write · schedule_update

Batched, typed, verified. Cycles are refused before they are applied, with the offending chain named. Two things this backend cannot do are not offered: reordering a task within the outline, and editing a calendar's weekly working-hours pattern. Asking for either gets a refusal that names it and says where to do it instead — an operation that half-works is worse than one that is absent.

Planningschedule_recovery · schedule_target · schedule_sequence · schedule_learn · schedule_generate

Reprogramming, measured rather than asserted. schedule_recovery finds what is late, ranks it by how much of the schedule sits behind it, then tries each recovery lever — removing lag on the driving chain, overlapping hand-offs, compressing the longest critical tasks — on a throwaway copy and reports the finish date each one genuinely produces. schedule_target tests a date you have been handed and names the work the network does not hold in place. schedule_sequence recovers the logic a schedule is missing by reading the order its own dates already state — the planner laid the work out correctly and never linked it, and that decision is recoverable. schedule_learn mines finished schedules for how long each activity actually takes and what usually comes before it; schedule_generate turns that into a first draft, one task per apartment or floor, sequenced the way the history says the trades follow each other.

Feed schedule_learn a model export alongside the schedules and it measures productivity — what a crew actually got through in a day — by joining quantities to tasks on the shared code. schedule_generate then sizes durations from the quantities of the new project rather than copying a remembered duration, because the rate is what carries between projects and the quantity is what changes. Give one export per schedule, in the same order: rates are measured per project, and quantities totalled across projects would inflate every one of them.

A draft can only be as well sequenced as the schedules it learned from. Where the sources link each activity to itself unit after unit but never to the trades around it, both tools say so and name the number: the library reports how many activities learned a predecessor other than themselves, and the draft reports how many trades it left with nothing scheduled before them.

Interopproject_export · project_import · bim_link · bim_sync

CSV, JSON, MSPDI, Primavera XER and PMXML, native .mpp, and a shaped Power BI dataset. Imports plan before they write.

What it costs to have loaded

The 25 tools present about 8,400 tokens of schema, in every prompt, for as long as the server is connected. That is the honest price of the surface and it is worth knowing before choosing to carry it. It is also why the surface stayed at 25: the largest alternative ships 79 tools, and past a point an agent cannot hold the surface in its head well enough to choose correctly within it.


The two contracts

Nothing is applied until it is verified.

{
  "applied": 12,              // operations that fully succeeded, re-read from the model
  "fieldsVerified": 31,
  "rejected": [{
    "uid": 45, "field": "finish",
    "requested": "2026-09-10", "actual": "2026-09-14",
    "reason": "'finish' is calculated from the task's duration and its predecessors. Change the
               duration or the logic, or set a constraint, rather than writing the date."
  }],
  "impact": {
    "tasksMoved": 312,
    "projectFinishBefore": "2027-03-14", "projectFinishAfter": "2027-03-28",
    "criticalPathChanged": true, "newNegativeFloat": 8
  },
  "verifiedBy": "reread"
}

A dry run is a real simulation. dryRun: true deep-copies the schedule, applies the batch, reschedules it with the critical-path engine, measures the difference, and throws the copy away. The impact numbers are observed, not predicted.


Capability honesty

project_health publishes a capability matrix, and the tools honour it. Two things stay false on the file backend and refuse rather than approximate:

  • write_native_mpp — no library can author the binary format. Where Microsoft Project is installed, the save is delegated to it and you get a genuine .mpp; where it is not, you get MSPDI and an explanation.
  • level_resources — Microsoft Project's levelling heuristic is unpublished. Any imitation would be a different answer wearing the same name.

Saving over a baseline that already holds data is refused too, unless you ask for it explicitly. A baseline is the record of the original plan that every variance is measured against, and it cannot be recovered from the file afterwards.

Everything else — scheduling, recalculation, dry-run simulation, rescheduling incomplete work, the DCMA Critical Path Test — is served by this server's own critical-path engine and works on both backends.

The critical-path engine — and what it is not

MPXJ reads and writes schedule files but does not schedule them: a task created through it has no dates at all. So there is a real CPM engine here — forward pass, backward pass, total and free float, critical flags — honouring relationship types, lag, constraints, deadlines, actual dates, and the working calendar per task (six-day site weeks, night shifts, exceptions you add with calendars_write). Without it, dates, float, earned value and every impact figure would be empty on any schedule this server authored.

⚠️ It is not Microsoft Project's scheduler

This engine reproduces Microsoft Project exactly on schedules built through this server. It does not reproduce it on real imported schedules. Measured against four production construction files, recalculating reproduced Microsoft Project's own start dates on 100% of tasks in one schedule, 69% in another, and around 23% in two more — where most of the remainder moved by a week or more.

Microsoft Project's scheduler has behaviours this engine does not implement: task types (fixed units, duration or work), effort-driven scheduling, resource calendars driving dates, manually scheduled tasks, split tasks, and elapsed durations. On a schedule that uses them, our dates will differ.

So imported schedules are never silently rescheduled. Open a .mpp and its dates stay exactly as Microsoft Project computed them; a write reports what it changed and says plainly that dates were not recalculated. If you want this engine's dates instead, ask for them explicitly with schedule_update op='recalculate' — which warns you first, and after which the document is ours rather than Project's.

Reading, querying, analysis, DCMA-14 and earned value all run on Microsoft Project's own dates and are unaffected. A dry run measures its impact against this engine on both sides, so the movement it reports is caused by your change rather than by the two engines disagreeing.

If Microsoft Project is installed, project_health reports the COM backend and you can hand the file back to Project itself for a native save.


Wiring it to a client

Claude Desktop, Claude Code, Cursor, VS Code — anything that speaks MCP over stdio:

{
  "mcpServers": {
    "horizun-msproject": {
      "command": "horizun-msproject-mcp"
    }
  }
}

Registry name: io.github.horizungroup/horizun-msproject-mcp (see server.json).

Call project_health first in every session — it tells you which backend you are on and what it can do.

Build and test from source

cd src/HorizunMsProjectMcp && dotnet build && cd ../..
python tools/acceptance-test.py   # 65 checks, all 20 tools end to end
python tools/scheduler-test.py    # 45 checks, critical-path engine correctness
python tools/planning-test.py     # 52 checks, reprogramming and learning
python tools/robustness-test.py   # 34 checks, concurrency and hostile input
python tools/smoke-test.py        # 13 checks, environment and capabilities

209 checks, driven over real JSON-RPC against the running server, on Windows and on Linux. The Linux job is the evidence for the headline claim: it runs on a machine with no JVM and no Microsoft Project.

The acceptance suite builds a construction schedule from nothing and asserts the contracts above: that a dry run commits nothing, that a cycle is refused before it is applied, that a write to an unknown uid is rejected rather than ignored, and that the DCMA Critical Path Test moves the finish date by exactly the delay injected into it.

The scheduler suite is the one that earns trust in the dates. It covers start-to-start, finish-to-finish and start-to-finish logic, positive and negative lag, hard and soft constraints, deadlines producing negative float, calendar exceptions actually pushing the schedule out, and a WBS hierarchy with summary rollup, that an imported schedule is never silently rescheduled, and full round trips through Primavera XER and PMXML and through a real binary .mpp — the last written by Microsoft Project itself, read back by MPXJ, with dates, milestone flags, budget codes and dependencies all intact.

Beyond the suites, the server has been driven through a planner's full working cycle on two production construction schedules — a 5,985-task programme and a 170 MB, 1,937-task one — opening, auditing, baselining, recording progress, measuring earned value and exporting the Power BI dataset, and read against files of up to 7,000 tasks.

The robustness suite is the one that matters for trusting this in a real client: forty writes in flight at once on the same document, hostile paths, absurd page sizes, non-latin names. MPXJ's object model is not thread-safe and an MCP client is free to pipeline calls — unguarded, sixty concurrent writes all failed and left the document unusable. Every document now has its own lock, reentrant because several tools are built on others.

A schedule stays in memory until it is closed, and a 170 MB one costs around 400 MB. Reading many retires the oldest document that has nothing unsaved; when every open document has unsaved work, opening another is refused rather than discarding any of it. project_health reports what is open and what it is costing.

Rebuild the installable package with dotnet pack -c Release.


Formats

Reads .mpp .mpt .mpx MSPDI .xml · Primavera .xer .pmxml · Asta .pp · Planner · GanttProject and more, through MPXJ.

Writes MSPDI .xml (Microsoft Project opens it natively) · .mpx · Primavera .xer and .pmxml · Planner · SDEF · JSON · CSV · Power BI dataset · native .mpp where Microsoft Project is installed.

Layout

src/HorizunMsProjectMcp/
  Diagnostics/   COM detection and the environment doctor
  Backends/      MPXJ I/O, the COM bridge, sessions and fingerprints
  Analysis/      critical-path engine, working calendar, DCMA-14, earned value
  Writes/        the verified-write engine
  Bim/           element matching and the 4D bridge
  Tools/         the 20 MCP tools
tools/
  acceptance-test.py   end-to-end across all 20 tools, 65 checks
  scheduler-test.py    engine correctness, format round trips, safety guards, 45 checks
  planning-test.py     recovery, sequencing, target dates, learning, generation, 52 checks
  robustness-test.py   concurrency, malformed input, resource limits, 34 checks
  smoke-test.py        environment and capability matrix, 13 checks

Design rationale and the market benchmark that motivated it: DESIGN-TOOL-SURFACE.md and BENCHMARK-MCP-MSPROJECT.md.

Licence

MIT.

Product Compatible and additional computed target framework versions.
.NET net8.0 is compatible.  net8.0-android was computed.  net8.0-browser was computed.  net8.0-ios was computed.  net8.0-maccatalyst was computed.  net8.0-macos was computed.  net8.0-tvos was computed.  net8.0-windows was computed.  net9.0 was computed.  net9.0-android was computed.  net9.0-browser was computed.  net9.0-ios was computed.  net9.0-maccatalyst was computed.  net9.0-macos was computed.  net9.0-tvos was computed.  net9.0-windows was computed.  net10.0 was computed.  net10.0-android was computed.  net10.0-browser was computed.  net10.0-ios was computed.  net10.0-maccatalyst was computed.  net10.0-macos was computed.  net10.0-tvos was computed.  net10.0-windows was computed. 
Compatible target framework(s)
Included target framework(s) (in package)
Learn more about Target Frameworks and .NET Standard.

This package has no dependencies.

Version Downloads Last Updated
1.0.2 443 8/4/2026
1.0.1 139 8/4/2026
1.0.0 111 8/4/2026